Khalid Port Berth Rehabilitation
CASE STUDY — QUAY WALL SHEET PILING & PORT WORKS

Khalid Port Berth Rehabilitation

Port Khalid, Sharjah • Sharjah

PROJECT NARRATIVE

Engineering Scope & Execution Highlights

Engineering Challenge

Construction of a 400-meter rock water bund in active tidal port conditions.

Execution Solution

Placement of graded rock materials and core bund construction in coordination with CHEC and Halcrow.

Comprehensive structural rehabilitation, steel sheet pile driving, and berthing quay wall remediation executed at Port Khalid, Sharjah for the Ports and Customs Authority.

Discuss a Similar Marine Project →

Project Fact Sheet

Location Port Khalid, Sharjah
Discipline Quay Wall Sheet Piling & Port Works
Client / Authority Sharjah Government
Consultant Halcrow
Main Contractor CHEC (China Harbour Engineering Company)
Contract Duration 4 months (2011–2012)
Khalid Port Berth Rehabilitation
EXECUTION PHOTOGRAPHY

Project Gallery & Site Progress

Authentic marine civil execution photography and site operations.

Khalid Port Berth Rehabilitation – Water Bund Works Site Execution
Khalid Port Berth Rehabilitation – Water Bund Works Site Execution